Latest Newsletter & Construction Underway
Well the day that us as developers and our amazing section purchasers have been waiting for has arrived. The issue of the new Titles…..

Titles Issued
Well the day that us as developers and our amazing section purchasers have been waiting for has arrived. The issue of the new Titles…..

224c Received!
This is one of the most exciting updates to date! We have received our 224C Certificate, which is now with Land Information NZ (LINZ) and our solicitor is working through the process of obtaining the titles.

224 Engineering Approval Received
Traffic resolution reports and naming of road extension applications all approved. All paperwork sorted with Auckland Council and 224 Certificate Received. We are now expecting 224c any day.
June 2024

Traffic Resolutions and Road Naming = Final Items
Traffic resolution reports and naming of road extension applications completed and supplied to relevant parties for approvals. This is quite a process with back and forth and then waiting for the Local Board and Auckland Transport Traffic Controls Committee to accept the final reports and applications onto their agendas and then approve them at their next scheduled meetings.
May 2024

Landscaping Establishing
The grass has taken well and is growing fast. The full subdivision got its first proper mow after works have finished. Street light testing and other inspections have been carried out by Auckland Transport.
March 2024

Final sign off for onsite works
Auckland Council final sign off of physical works and lodging and processing started for Auckland Transport.
January 2024

Completion of Subdivision Construction Works
Completion of all subdivision construction & physical works on site completed and final inspections underway. A great milestone for the team to hit before the end of the year!
December 2023

Final Stages of Subdivision Construction
The final stage of physical subdivision construction is nearing completion with 223 sign off received and compliance paperwork and sign offs all starting to roll in ready for 224(c) and lodging for the new titles. Very exciting times.
November 2023

First monthly newsletter sent out
Our first monthly newsletter went out with updates about the development and interesting information about the community. Make sure to sign up to our newsletter with the “Take Action” button and then enter your details to sign up to the mailing list.
April 2022

Final Release of Sections for Sale
Get in now to secure the last available sections. There are so many reasons to create your dream property in this amazing location.
April 2022

Final Stages of Engineering Approvals
We are now down to the final few items with Auckland Transport on the new road which will be constructed to extremely rigorous and robust engineering standards. It looks like this should be approved in April ready to start full civil construction soon after.
March 2022

Surveyors Initial Pegs & Bulk Earth Works Underway
The surveyors have been onsite an completed the initial pegs and the bulk earthworks that can be done have been completed.
February 2022

Environmental protections & Site set up works
Installation of environmental protections and silt controls and construction fencing and gates.
December 2022

First Sales Release
First Release of Sections to the market was very successful with 6 sections sold.
July 2022